This project involved extensive mechanical and electrical renovations at Jackson and Wilson Elementary Schools. Key strategies included managing long lead times for HVAC equipment through proactive supplier engagement and proposing cost-effective solutions based on field conditions. The renovation schedule prioritized a fast-paced summer phase, supported by off-site prefabrication to improve quality and efficiency. Night and weekend work leading up to the summer phase helped ensure accelerated progress during the school break. Our team also developed multiple contingency plans to ensure the schools were ready for teachers and students at the start of the school year.